Scheme programme
For the scheme, we will be working to the following programme*:
*Please note these dates are indicative and may change
Podimore to Downhead
Works to connect to Podimore Roundabout
December 2022 – November 2023
Construction of the new Camel Cross junction
January 2022 – November 2023
Excavating earth and building levels for new road alignment
May 2022 – June 2023
Construction of the new section of road
May 2022 – November 2023
Downhead to Steart Hill
Construction of the new Steart Hill bridge
November 2021 – September 2022
Temporary internal road and bridge over the A303 for construction site
September 2021 - March 2023
Excavating and building levels for the new road alignment
August 2021 – February 2023
Construction of the new section of road
April 2022 – November 2023
Building of local roads that will connect to Downhead and Steart Hill
April 2022 – November 2023
Steart Hill to Hazlegrove
Construction of the new Hazlegrove underpass
December 2021 – September 2022
Temporary road within construction site
September 2021 - March 2023
Excavating and building levels for new road route
September 2021 – June 2023
Construction of the new section of road
June 2022 – November 2023
Building of local connecting roads, work on Hazlegrove roundabout and slip roads
January 2022 – November 2023
- Downloads
- Works starting in 2021 map