Scheme programme

                                                             

For the scheme, we will be working to the following programme*:

*Please note these dates are indicative and may change

Podimore to Downhead

Works to connect to Podimore Roundabout
December 2022 – November 2023

Construction of the new Camel Cross junction
January 2022 – November 2023

Excavating earth and building levels for new road alignment
May 2022 – June 2023

Construction of the new section of road
May 2022 – November 2023

Downhead to Steart Hill

Construction of the new Steart Hill bridge
November 2021 – September 2022

Temporary internal road and bridge over the A303 for construction site
September 2021 - March 2023

Excavating and building levels for the new road alignment
August 2021 – February 2023

Construction of the new section of road
April 2022 – November 2023

Building of local roads that will connect to Downhead and Steart Hill
April 2022 – November 2023

Steart Hill to Hazlegrove

Construction of the new Hazlegrove underpass
December 2021 – September 2022

Temporary road within construction site
September 2021 - March 2023

Excavating and building levels for new road route
September 2021 – June 2023

Construction of the new section of road
June 2022 – November 2023

Building of local connecting roads, work on Hazlegrove roundabout and slip roads
January 2022 – November 2023